Between the early 1990s and 2018, an estimated 700 PFI contracts were entered into. Over one-fifth of those are due to expire within the next decade, triggering the handback process whereby private sector service providers return assets to the public sector.
When PFI contracts were introduced, the theory behind them was laudable in the eyes of many: use the private sector to finance public works projects, with the public sector then repaying those funds over the course of the project instead of having to source and invest capital up front.
Unfortunately, in many instances, the reality of PFI contracts in practice (due to the many problems the public sector has faced and still faces) meant the PFI model became more laughable than laudable. One such problem is that of monitoring and ‘self-reporting’, whereby the terms of the PFI contract require the private sector service provider (the “Contractor”) to monitor its own performance and report back to the public authority on that performance and any service failures.
This methodology presents a plethora of challenges that public authorities are facing everyday:
Firstly, there is the question of trust: can a private sector Contractor be trusted to self-report where it has failed in its performance?
Because most PFI contracts hold Contractors to account by enabling the public authority to make deductions to payments in response to performance failures, an under-performing Contractor will want to minimise what information is fed back to the public authority. This could mean withholding information that would be detrimental to their income. Contractors are also enticed to monitor in a manner that reduces the chances of becoming aware of a failure that it would have to report (thus opening up an argument that you can’t self-report on a failure you don’t know about).
This is a very real problem for public authorities operating PFI contracts, as the case of Compass Group UK and Ireland Ltd (t/a Medirest) v Mid Essex Hospital Services NHS Trust 2012 shows. Here, the Contractor failed to provide reports for the first three months of the contract and didn’t report some of its own performance failures (these were instead identified by the Trust). The case even identified an occurrence where the Contractor omitted pages of an inspection report by a health and safety expert that identified a number of areas where improvement should be completed with immediate effect.
Let’s say hypothetically all PFI Contractors could be trusted to monitor their own performance appropriately and fully self-report.
The next question is how can public authorities validate and authenticate the information and data provided in the Contractor-provided reports?
At a time when the budgets of most public sector bodies are stretched, many do not have the resources in terms of finance, time and expertise to review regular Contractor reports to the extent required and, on top of that, conduct their own monitoring to check the reports are correct. That’s if it is possible for the public authority to comprehend the reports in the first place, given that often they can be incredibly complex and overflowing with data.
Furthermore, there’s the question of whether public authorities should have to monitor PFI contract performance for themselves?
After all, monitoring and self-reporting are commonly part of the service for which the Contractor is paid.
From the Contractor perspective, in many instances they too are frustrated by the concept of monitoring and self-reporting. Many PFI contracts often aren’t clear on what exactly needs monitoring, how to monitor it and how to report it. This frequently results in a situation where Contractors, even with the best will in the world, may not be able to monitor and report upon PFI performance effectively. In this scenario, neither party is satisfied because the Contractor may be delivering the service appropriately but struggle to monitor and report on the performance in accordance with the contract requirements, driving the public authority to push for improved monitoring and reporting, perhaps unnecessarily. Over time, the relationship between the parties can deteriorate and disputes often follow.
Given the problems outlined above, what can parties bound by the limitations of monitoring and self-reporting in PFI contracts do moving forward?
First and foremost, any public authority that has not already introduced some form of monitoring conducted by itself or a third party would be wise to. As outlined above, even where self-reporting by a Contractor is occurring, possible errors, oversights and omissions in reports could mean that performance is not meeting the standards the public authority requires.
Of course, additional monitoring by the public authority will add a new expense at a time when public bodies’ resources are already strained. Where ongoing monitoring by a public authority isn’t possible, whether due to limited resources or lack of expertise (or both), at the very least they should be implementing a process whereby they regularly review the reports provided by the Contractor and undertake spot checks to ensure the Contractor’s reports provide an accurate picture of performance. In instances where a Contractor fails to adequately monitor its performance, provide reports or self-report on service failures, public authorities should seek to strictly enforce the terms of the PFI contract.
Another option is to pursue a variation to the monitoring and reporting terms of the PFI contract. This approach could make monitoring and reporting obligations clearer for all parties which in turn could reduce the likelihood of any disputes arising. However, any public authority that considers this option should be aware that where a contract’s terms favour the Contractor, the Contractor may push back against any notion of changing or increasing its obligations. Furthermore, even where the Contractor consents to changing the monitoring and/or self-reporting obligations, the public authority may go to the expense of negotiating and implementing the contract variations only to find that the underlying problems that undermine self-reporting mean the public authority still doesn’t receive accurate reports and service failures continue to go under or even unreported.
The stark reality is that self-reporting in PFI contracts favours Contractors. While one-fifth of PFI contracts will be coming to an end in the next few years, many have plenty of years left to run. Where this is the case, it may be beneficial for public authorities to seriously consider the options outlined above to address the limitations of monitoring and reporting in their PFI contracts and find a better way of working within the terms of their contracts.
Browne Jacobson’s experienced teams are available to advise on the options outlined above and on other PFI contract matters.
Contact
Discover more
You may be interested in...
Legal Update
Employment Rights Bill: Will it cost more to outsource public services and back-office functions?
Guide - PFI expiry
PFI expiry guidance for schools
Legal Update
Know your dispute resolution clauses: Key take-aways from Kajima v Children’s Ark and Lancashire Schools v Lendlease
Press Release
Browne Jacobson and CBI roundtable explores how to finance public infrastructure post-PFI
Press Release
King’s Speech 2024: Reaction from Browne Jacobson lawyers
Legal Update - PFI expiry
A first of many? PFI company seeks Restructuring Plan
Legal Update - PFI expiry
Managing PFI contract expiry and maintaining party relationships
Legal Update - PFI expiry
PFI handback: ‘Handback Condition’ limitations, disputes and solutions
Legal Update
2024: Horizon scanning in construction
Legal Update - PFI expiry
Managing the expiry of PFI contracts
Legal Update - PFI expiry
PFI expiry - hope for the best, plan for the worst?
Legal Update
What are we to do about self reporting in PFI contracts?
Press Release
Browne Jacobson advise London borough councils on key social infrastructure PFI deal for streetlighting in Croydon and Lewisham
Legal Update
Higher education projects – the end is nigh?
Published Article
How the Environment Act affects existing contracts’
Press Release
Browne Jacobson advises Bromley Council on the first social housing initiative of its kind to tackle homelessness
Published Article
The role of Legal Project Management in public sector projects
The concept of Legal Project Management (“LPM”) is increasingly relevant to the delivery of legal services, both in-house functions and private practice law. This is unsurprising, LPM is crucial if lawyers are to add value by controlling budgets, communicate pro-actively on risk mitigation and costs, and manage time by resourcing to deal with pinch points in the project.
Legal Update
Regeneration funding: Securing Compulsory Purchase Orders in the face of escalating building costs
The focus on the Levelling Up agenda and the availability of grant funding, means there are numerous important regeneration schemes actively being pursued across the country. With ever-escalating project and building costs, in many cases, applications that were made for grant funding were based on costs contingencies that have already been exceeded.
Legal Update - PFI expiry
The impending termination of PFI contracts and what should be done now
Press Release
Browne Jacobson’s government & infrastructure lawyers advise on first South West based green hydrogen production project
Browne Jacobson’s specialist government and infrastructure team have advised Canford Renewable Energy Ltd on the delivery of its Dorset Green H2 facility.
Guide
2022: Horizon scanning in construction
Published Article
Construction needs to do more to reduce carbon emissions
More needs to be made of these procurement routes, with clients honouring the original concept rather than watering down concepts.
Legal Update
Waste is only waste if we waste it*
This article looks at the impact of Part 3 of the Environment Act 2021 on waste collection authorities, including measures to reduce packaging waste, to encourage re-use and recycling and changes to the way waste will be collected.